Ujj Multipurpose Project In Jammu And Kashmir Cost Increased By Rs 2741 Crore

News Desk, Amar Ujala, Jammu

Published by: Prashant Kumar
Updated Sat, 30 Oct 2021 02:05 PM IST

Summary

On the instructions of the Center, the Chief Secretary has assured to send the MoU on the revised cost within 15 days.

The cost of the Ujj Multipurpose Project has increased by Rs 2741 crore. Now the project will cost Rs 11908 crore. Earlier its cost was Rs 9167 crore. Ninety percent funding of the project is done by the central government and 10 percent by the state government. Therefore, before approving the revised cost, the central government needs the concurrence of the state government. The central government has asked the state government to give consent for funding.
Also read- Jammu and Kashmir: Movement of terrorist organizations intensified in PoK, terrorist infiltration may increase in Rajori and Poonch before snowfall

The central government has announced to approve the second phase of Jhelum river flood management in two months. The Home Ministry on Friday reviewed the works of the Prime Minister’s Development Package by holding a high-level meeting with the officials of the Government of Jammu and Kashmir and Punjab. In the meeting held under the chairmanship of Piyush Goyal, Additional Secretary, Ministry of Home Affairs, it was informed that the irrigation potential of Shahpur Kandi Project is 53927 hectares of land. With this the irrigation needs of Samba and Kathua districts can be met.

It was told that the land acquisition process has been started on the banks of Ravi Canal. As soon as the compensation process is completed, the Punjab government will be informed about it. 192 kanals of land is to be acquired for the project. Out of this, only five percent land is left to be acquired. The land has been handed over to the construction company. The work could not start due to non-handing over of the small piece of land.

In the meeting, Chief Secretary Dr. Arun Kumar Mehta told that in the next 15 days, after determining the amount of compensation, the information will be given to the Punjab Government. The representative of the Punjab government said that due to water in Shahpur Kandi reservoir, a part of Lakhanpur-Basohli road has been absorbed. The Chief Secretary directed the Administrative Secretary, Jal Shakti Department that the road should either be realigned or an alternate bridge and road project should be prepared so that the work of the reservoir could be completed by the Punjab Government in the first quarter of 2023. There should not be any road blockage in the project.

Expansion

The cost of Ujj Multipurpose Project has increased by Rs 2741 crore. Now the project will cost Rs 11908 crore. Earlier its cost was Rs 9167 crore. Ninety percent funding of the project is done by the central government and 10 percent by the state government. Therefore, before approving the revised cost, the central government needs the concurrence of the state government. The central government has asked the state government to give consent for funding.

Also read- Jammu and Kashmir: Movement of terrorist organizations intensified in PoK, terrorist infiltration may increase in Rajori and Poonch before snowfall

The central government has announced to approve the second phase of Jhelum river flood management in two months. The Home Ministry on Friday reviewed the works of the Prime Minister’s Development Package by holding a high-level meeting with the officials of the Government of Jammu and Kashmir and Punjab. In the meeting held under the chairmanship of Piyush Goyal, Additional Secretary, Ministry of Home Affairs, it was informed that the irrigation potential of Shahpur Kandi Project is 53927 hectares of land. With this the irrigation needs of Samba and Kathua districts can be met.

It was told that the land acquisition process has been started on the banks of Ravi Canal. As soon as the compensation process is completed, the Punjab government will be informed about it. 192 kanals of land is to be acquired for the project. Out of this, only five percent land is left to be acquired. The land has been handed over to the construction company. The work could not start due to non-handing over of the small piece of land.

.